PENJADWALAN MESIN SCREW PRESS STASIUN KEMPA PADA PRODUKSI CPO (CRUDE PALM OIL) DAN KERNEL DENGAN MENGGUNAKAN METODE INDIKATOR

Authors

  • Heri Wibowo Program Studi Teknik Industri Universitas Malahayati

DOI:

https://doi.org/10.12928/si.v14i1.3703

Abstract

Complex problems often encountered in the company, especially the production. The company should be
able to increase production capability by increasing the utility of existing resources and accuracy in the
completion of production to match the deadlines set by scheduling planned well. As a company produces
CPO and kernel continuously so the scheduling screw press machine should be well planned so that
production can be completed on time, damage to the engine and overtime can be avoided. This study aims
to analyze the utilization schedule and screw press machine at the station felt that optimal production can
be achieved and determine the cause of the delay production time resulting in overtime. The method used
is the method of indicators that can be applied to the machine which is parallel with different capacities.
This method minimizes the turnaround time by prioritizing machine with a large capacity while
maintaining the efficiency of the engine and the completion time has been determined. Proposed
scheduling using indicators generate optimal schedule, 13840 hours of work available only used 12373.5
hours with five machine screw press, the clock difference is 1408.5 hours of work hours are unemployed
and 58 hours of treatment machine screw press, and produce five utilities screw press machine on
average up to 89.40% and utilities average every month five screw press machine is 89.46%. The delay
time of CPO production process and the kernel has been caused by damage to machine screw press
which occur during the production process takes place so that if the production capacity is reduced and
overtime hours cannot be avoided. Screw press machine maintenance can be done by the engine
maintenance schedule time without having to wait for the machine was broken beforehand and this can
reduce the cost of production.

Keywords : Indicator Method, Scheduling Engine